|
PROJECTS |
STATUS |
|
Charlotte Cotton Mills |
Phase II major interior and
exterior stabilization is 99% complete. Remaining work on this contract
is on the exterior. Fire sprinkler system upgrades have been completed.
Phase III construction is well underway with completion scheduled for
late August 2003. |
|
Oehler Farm |
Consultant is awaiting comments
from Archives and History Office. Consultant has been advised that
construction has been put on hold until funding is available. Consultant
is proceeding with construction document development. |
|
Rozzell House |
Architect is 99% complete with
construction drawings. Consultant has been advised of budget reduction
and is preparing bid alternates. Anticipate bidding project in early
Sept 03. Certificate of Appropriateness was approved @ the 25 Feb. 03
Design Review Committee Meeting. National Registry documentation has
been completed and submitted. Tenant has vacated main house in
preparation of construction. |
|
McAuley House |
Second Design review has been
completed. Consultant is awaiting comments from Archives and History
Office. Selective interior removal/demolition has begun to allow access
for structural evaluations. Consultant has been advised that
construction has been put on hold until funding is available. Consultant
is proceeding with construction document development. |
|
Palmer Fire School |
Barwick Associates has begun
restoration of the Assembly Building with anticipated completion id Sept
2003. |
|
George E. Davis House |
Bethune, Nystrom and Turner met
with representative of JCSU on 28 Mar 03. Gantt Huberman Architects will
develop construction documents for JCSU with consultation with HLC
staff. Budgets and fees have been revised by GH and are awaiting
decision form JCSU board concerning their financial commitment to the
project. |
|
Croft School House |
Sale has been completed.
Purchasers are occupying the building. |
|
W.T. Alexander Plantation |
Exterior restoration is complete.
New underground utility installation is complete. Apprasial has been
ordered. Discussions with Barwick Associates continue. Ref; Access
Easement: HLC Attorney has contacted the apartment developer's legal
representative. Discussions were encouraging. Their legal representative
is new to the company and was not involved in the original negotiations.
We have forwarded specific information to him and he was to become more
familiar with the property and our access issue for future discussions.
We have asked the land surveyor that developed the original plot
plans for W.T. Alexander site to verify the location of all the
improvements accomplished by the apartment developer along the boundary
between the HLC tract and the apartments in an effort to exactly
determine there respective location and to help identify the reason(s)
the street was not turned over to the city of Charlotte. |
|
Grier-Rea House |
Foundation construction and repair
of the lower level under floor system, foundation walls, and internal
piers is complete. National Registry nomination is complete. Consultant
is awaiting clarification of certain design review issues from Archives
and History Office. A/E and Staff are developing Scope of Work for
Second Phase. |
|
Grier House |
Site cleanup, exterior, and
interior hazardous material removal is completed. Building has been
boarded up to prevent vandalism. Portrait Homes has completed demolition
of all other existing structures on the site and have construction
underway. Architect has completed construction documents. Documents are
being reviewed by contractors with bids to be received 21 Aug 2003. |
|
Trolley Car Barn |
City and CATS staff are reviewing
survey to determine if parcel indicated to be purchased by the County is
adequate for the needs of CATS and Charlotte Trolley. |
|
Rural Hill School House |
Construction has been completed.
|
|
Grand Theater |
Purchase will be completed 30 May
2003. Tennant has been asked to vacate. Building will be secured
indefinitely. |
|
Yandell House |
Purchase is complete. Minor
stabilization and repairs have begun including roofing, gutter, and
interior finish repair. Extensive landscape maintenance is required and
has begun. "For Sale" sign is being developed, anticipate installation
around 1 Sept 03. |