Oehler
Farm |
Stabilization Design Continues. 2nd Design review is underway by staff. |
|
Rozzell
House |
Architect
is approx 90% complete with construction drawings to reflect changes
requested by Design Review and Projects committee. Staff has
completed a second design review. Awaiting review comments from NC
Dept. Achieves and History. Architect & PM will meet @ the site on 30
Jan 03 with NC Dept. Achieves and History representative. |
|
McAuley
House |
Stabilization Design is on hold due to access to site and weather
conditions. Purchase offer has been retracted. |
|
Palmer
Fire School |
Staff has
completed due diligence items requested by purchaser. Anticipated
closed date late February 2003. |
|
George
E. Davis House |
No Status
Change. Architect for JCSU has advised that rezoning has been approved,
October 02. County Attorney is awaiting documentation from JCSU
Attorney concerning property transfer. |
|
Croft
School House |
Discussions
continue with MECA Properties and the potential purchaser concerning tax
credits, etc. |
|
W.T. Alexander Plantation |
Exterior
restoration continues. Progress has been drastically impacted by
weather conditions. Draft RFP will be available @ the 3 Feb Projects
Meeting |
Grier-Rea House
|
Demolition
of Krueger House is complete. Site preparation for foundations has been
completed. Foundation construction is anticipated to begin during the
week of 27 Jan 03. House to be relocated to the new site during the
week of 10 Feb 03. Progress has been extensively delayed due to
weather. |
|
Grier House |
Purchase is
complete. Site cleanup and exterior hazardous material removal has been
completed. Architect anticipates beginning documentation of existing
conditions in early Feb. 03. Building has been boarded up to prevent
vandalism. Portrait Homes anticipates construction to begin in Feb 03
with their model units to be open in Oct 03. |
|
Trolley Car Barn |
Defer for
Consulting Director. |
|
Rural Hill School House |
Bids for
construction were received on 29 Jan 03. Architect will be @ the 3 Feb
03 projects Committee meeting to present results. A request for
additional funding will be required to complete installation of two
restrooms @ the facility. Additional information will be presented @
the meeting. |